The watermain replacement in the Old Nags Head Cove Subdivision is nearing completion with the watermain installation complete. Testing of the installed watermain is ongoing.
The sequence for bringing the section of watermain online is as follows:
- S. Pamlico Way/Tarpon Ct./Amberjack Ct./Dolphin Ct.: switchover to occur the week of Sept. 12th, likely around September 13th/14th
Driveway replacements will continue to be completed along S. Pamlico Way, Tarpon Ct., Amberjack Ct., Dolphin Ct., and W. Sandpiper Ct.
If you have any questions pertaining to project construction, please do not hesitate to contact David Ryan, P.E. at 252.441.6221 or david.ryan@nagsheadnc.gov. For additional information related to project construction, please visit the Town's website at Engineering | Nags Head, NC (nagsheadnc.gov).
We thank you for your patience during project construction.