The watermain replacement in the Old Nags Head Cove Subdivision is nearing completion with the watermain installtion complete. Testing of the installed watermain is ongoing.
The sequence for bringing the section of watermain online is as follows:
- S. Blue Marlin Way: scheduled for Sept. 2nd and Sept, 6th.
- Albacore Drive: scheduled for the week of Sept. 5th
- S. Pamlico Way/Tarpon Ct.: testing to commence the week of Sept. 5th
- Amberjack Ct./Dolphin Ct./W. Sandpiper Ct.: to proceed w/testing following S. Pamlico Way.
Driveway replacements will continue to be completed along S. Pamlico Way, Tarpon Ct., Amberjack Ct., Dolphin Ct., and W. Sandpiper Ct.
If you have any questions pertaining to project construction, please do not hesitate to contact David Ryan, P.E. at 252.441.6221 or david.ryan@nagsheadnc.gov. For additional information related to project construction, please visit the Town's website at Engineering | Nags Head, NC (nagsheadnc.gov).
We thank you for your patience during project construction.