The FY 22 sidewalk project construction is coming to a completion the week of February 21st. Sidewalk installation was focused between the intersection of W. Baymeadow Dr./W. Seachase Dr. through to S. Croatan Hwy. Work will proceed on the east side of S. Croatan Hwy. the week of along Seachase Dr. with construction of an accessible ramp with associative concrete curb and gutter. This final section will complete the FY 22 sidewalk construction.
We ask that motorists and pedestrians exercise caution when circulating around the active construction zone.
If you have any questions, please feel free to contact David Ryan, P.E. at 252.441.6221 or at david.ryan@nagsheadnc.gov.