Approximately three miles of watermain will be replaced in Old Nags Head Cove starting about mid-January 2022. If the work is not completed by May 20, 2022, the contractor is required to temporarily cease construction until September 15, 2022.
Watch a video about the project.
A virtual meeting was held on January 6, 2022 at 6 pm. Watch a video of the meeting.
If you know of someone who is unable to attend or listen to the meeting (we'll post a link to a recording of the meeting here), please have them contact Town Engineer David Ryan with any questions. His phone number is 252-441-6221.