[ARCHIVED] Beach Restoration Starting Mid-July

Beach Restoration 2022

A beach restoration project is taking place this summer from 8031 South Old Oregon Inlet Road (Comfort Inn South) near Mile Post 16 south to Nags Head's corporate limits abutting Cape Hatteras National Seashore near Mile Post 21. 

*Oceanfront properties and public beach accesses along South Virginia Dare Trail will NOT be impacted by the project.

A construction progress map will be updated daily during the project to provide the latest beach closure information. 

July 19, 2022 Schedule Update

Project construction is now expected to begin on Friday, July 22, 2022. 

July 12, 2022 Schedule Update

Construction is expected to begin the middle of next week, most likely on July 20, 2022, just south of Limulus Drive, near 10011 South Old Oregon Inlet Road in south Nags Head. Over the next 7-10 days, construction will move south to the south end of the project area at 10435 South Old Oregon Inlet Road. 

Once the first section is complete, construction will return to the area near 10011 South Old Oregon Inlet Road and move north to about 9405 South Old Oregon Inlet Road over 5-7 days, where construction will cease until mid-to-late August

In mid-to-late August, a second dredge will arrive and construction will begin near 9021 South Old Oregon Inlet Road and progress south to near 9405 South Old Oregon Inlet Road. Then, construction will return to near 9021 South Old Oregon Inlet Road and proceed north to near 8645 South Old Oregon Inlet Road (station 855). This phase of construction should be completed by the end of August or the beginning of September. 

Construction will then begin near 8407 South Old Oregon Inlet Road and proceed south to near 8645 South Old Oregon Inlet Road. Then, construction will return to near 8407 South Old Oregon Inlet Road and progress north to 8031 South Old Oregon Inlet Road, which is the northern end of the beach restoration project area. This phase of construction should be completed by the middle of September. 

View videos from our 2019 beach nourishment project to get a better idea of what construction entails. 


Photo of Beach with Text Receive Beach Restoration Progress Updates

(Choose the 2022 Beach Restoration Construction Schedule Updates list under Notify Me)

Facebook Twitter Email