A beach restoration project is taking place this summer from 8031 South Old Oregon Inlet Road (Comfort Inn South) near Mile Post 16 south to Nags Head's corporate limits abutting Cape Hatteras National Seashore near Mile Post 21.
*Oceanfront properties and public beach accesses along South Virginia Dare Trail will NOT be impacted by the project.
July 19, 2022 Schedule Update
Project construction is now expected to begin on Friday, July 22, 2022.
July 12, 2022 Schedule Update
Construction is expected to begin the middle of next week, most likely on July 20, 2022, just south of Limulus Drive, near 10011 South Old Oregon Inlet Road in south Nags Head. Over the next 7-10 days, construction will move south to the south end of the project area at 10435 South Old Oregon Inlet Road.
Once the first section is complete, construction will return to the area near 10011 South Old Oregon Inlet Road and move north to about 9405 South Old Oregon Inlet Road over 5-7 days, where construction will cease until mid-to-late August.
In mid-to-late August, a second dredge will arrive and construction will begin near 9021 South Old Oregon Inlet Road and progress south to near 9405 South Old Oregon Inlet Road. Then, construction will return to near 9021 South Old Oregon Inlet Road and proceed north to near 8645 South Old Oregon Inlet Road (station 855). This phase of construction should be completed by the end of August or the beginning of September.
Construction will then begin near 8407 South Old Oregon Inlet Road and proceed south to near 8645 South Old Oregon Inlet Road. Then, construction will return to near 8407 South Old Oregon Inlet Road and progress north to 8031 South Old Oregon Inlet Road, which is the northern end of the beach restoration project area. This phase of construction should be completed by the middle of September.
July 8, 2022 Schedule Update
Construction is being delayed due to expected high surf, so the project start may be delayed a few days.
The plan, as it is today, is for construction to begin near 10011 South Old Oregon Inlet Road and proceed south to 10435 South Old Oregon Inlet Road, where the southern end of the project area. Then, construction will return to near 10011 South Old Oregon Inlet Road and proceed north to about 9405 South Old Oregon Inlet Road. This phase of construction should be completed by the end of July or the beginning of August.
In mid-to-late August, a second dredge will arrive and construction will begin near 9021 South Old Oregon Inlet Road (station 888) and progress south to near 9405 South Old Oregon Inlet Road. Then, construction will return to near 9021 South Old Oregon Inlet Road and proceed north to near 8645 South Old Oregon Inlet Road. This phase of construction should be completed by the end of August or the beginning of September.
Construction will then begin near 8407 South Old Oregon Inlet Road and proceed south to near 8645 South Old Oregon Inlet Road. Then, construction will return to near 8407 South Old Oregon Inlet Road and progress north to 8031 South Old Oregon Inlet Road, which is the northern end of the beach restoration project area. This phase of construction should be completed by the middle of September.
June 28, 2022 Schedule Update
Beach restoration project construction is now expected to take place from July 13 through early September 2022.
Equipment mobilization is underway and de-mobilization is expected to take place in September.
Remember, it is likely the schedule will change over the course of the project.
A construction progress map will be updated daily during the project to provide the latest beach closure information.
View videos from our 2019 beach nourishment project to get a better idea of what construction entails.