Construction is underway on the W. Danube St. Drainage Replacement Project:
Replacement of the existing W. Danube St. drainage infrastructure began earlier this week. The temporary road closure which was employed along W. Old Cove Rd. on Thursday March 4, 2021 has been removed and is open to vehicular traffic. A temporary gravel surface has been placed in the area of the asphalt roadway cut. We ask that motorists exercise caution when driving between W. Old Cove Rd. and W. Danube St.
To date, the storm pipe has been replaced through to the W. Old Cove Rd./W. Danube St. roadway intersection. Work will resume early next week between the intersection of W. Old Cove Rd. and S. Croatan Hwy.
If you have any questions, please call David Ryan, P.E. at 252.441.6221.
We thank you in advance for your patience while construction work is being conducted.